Anger over pitch delay at Derry's Brooke Park


A group which represents users of a Derry leisure facility have hit out after it emerged that a new synthetic pitch set to open for the summer at the site will not open until the end of this year.
The Brooke Park Users Forum have claimed that they were initially told by council that the new synthetic pitch would be up and running at the area formerly occupied by the old tennis courts by the end of May.
The synthetic pitch is one of a number of new facilities planned as part of the overall £5.6m regeneration of Brooke Park.
The Forum have claimed they were then told that due to delays caused by the re-development work being put back out to tender, the pitch would be available for use by July of this year at the latest.
However, Derry City and Strabane District Council has now confirmed that the pitch will not be completed by October/November of this year, which has prompted an angry response from the group.
The Derry News revealed in October of last year how work had stalled at the park after the preferred bidder pulled out.
Derry City Council announced the transformation of the park in June 2013, with a completion date of Autumn/Winter 2015, which was then pushed back to Spring/Summer 2016.
Council hope that the completion date can still be met by reducing the construction period from 18 to 15 months.
Woodvale Construction was then appointed as the main contractor for the re-development of the park at the start of this year, with work re-commencing in February.
Speaking to the Derry News yesterday, Dalton Kehoe of the Brooke Park Users’ Forum said that the news was ‘disappointing’.
“We were told before Christmas that the pitch would be available for March, weather permitting, and if not, then we were looking at April or May,” he said.
“After the discovery of an electric cable we were told that another few weeks would have to be added on to the schedule, then we were told that at the very latest, it would be ready for July, where we would have use of it after 6pm, after the site traffic and work had stopped for the day.
“Now we’re being told that it’s going to be more or less the end of the year before it’s ready, so it’s very disappointing that the completion date keeps getting pushed back.
“It’s being used as a compound and a temporary car park for the workers on site, yet part of the agreement with the user group and the council was that priority would be given to the synthetic pitch.”
He added: “The hope was that even if had opened in July then the young people in the community would have gotten good use out of it during the summer, and that it may have also helped address the anti-social behaviour which seems to plague this area around that time.”
Mr Kehoe added that the Forum has also sought to obtain a planned timescale of works for the Brooke Park regeneration project, but had received nothing to date.
A spokesperson for Derry City and Strabane District Council said that that it ‘engages regularly with Brooke Park user groups in relation to this significant investment project for the city’.
“Sectional completion of the synthetic pitch was previously agreed and communicated to the User Group to be within the first 35 weeks of the overall 64-week construction programme,” the spokesperson said.
“Given that work commenced on site in February 2015 means that this facility would be completed by October/November 2015 and not May 2015.”
The spokesperson added that Council ‘remains committed to keeping all interested parties appraised of ongoing developments on a regular basis and confirm that the project remains on programme as tendered’.